How Big Should Your Theme Park’s Audience Be?

If you want to build a theme park with a capacity of 25,000 people at any given moment, serving people who live within one hour of travel time, and the following assumptions are true:

  • The park operates during the year but not in summer.
  • 60% of the population is interested in visiting the park.
  • 40% of the population will not visit the park.
  • During peak times, the park can host up to 25,000 visitors simultaneously.

How can I solve this?
 

3
500+
39
Be the first to answer!
Nobody has responded to this question yet.
Top answer
Hagen
Coach
on Dec 09, 2024
#1 recommended coach | >95% success rate | 9+ years consulting, interviewing and coaching experience

Hi there,

I would be happy to share my thoughts on your question:

  • First of all, can you please provide a proposal that I can review?
  • Moreover, several pieces of information are missing, such as opening hours, average time spent in the theme park, and average occupancy. Thus, without this information, and contrary to what other coaches have said, it is impossible to estimate the required size of the theme park's audience.

You can find more on this topic here: How to succeed in the final interview round.

If you would like a more detailed discussion on how to best prepare for your upcoming discussion, please don't hesitate to contact me directly.

Best,

Hagen

Deleted user
on Dec 01, 2024

Hi there,

To determine the required audience for your theme park:

  1. Daily attendance assumption: assuming 80% utilization of the park’s 25,000 capacity, the average daily attendance is 20,000 visitors
  2. Annual park capacity: with 250 operational days (accounting for summer closure), total capacity = 20,000×250=5,000,000
  3. Visits per person: assuming each person visits 1.25 times per year (average between occasional and frequent visitors), the required population of interested visitors is 5,000,000/1.25=4,000,000
  4. Adjust for interest rate: since only 60% of the population is interested, the total population required is 4,000,000/0.6=6,666,667

Conclusion: You need about 6.7 million people within one hour of the park to achieve full capacity, assuming 80% utilization, 250 operational days, and 1.25 visits per person annually.

Please note that the actual result doesn't matter. The reasoning and assumptions are key here, and showing how you justify them is often more important than the precise numbers.

Hope it helps!

Best,
Oumar

15
Anonymous A
on Dec 04, 2024
Why do we divide by 60% rather multiplying
Deleted user
Coach
on Dec 09, 2024
Sorry, just saw your comment. Because I need 4M but only 60% of the town is interested in visiting thus my 4M=60% of the town. Therefore, the population in my town needs to be equal to 4M/60%
I hope it helps.
Best!
Alessa
Coach
on Dec 01, 2024
xMcKinsey & Company | xBCG | +200 individual & group coachings | feel free to schedule a 15 min intro call for free

Hey! 

I would probably do the following: 

Determine the potential population within a one-hour travel radius: This gives you the base number of people in your target market area.

Apply the interest rate: Multiply the total population by 60% to find the number of people interested in visiting.

Adjust for frequency of visits: Consider how often the interested individuals are likely to visit (e.g., once a year, multiple times, or only occasionally).

Account for capacity constraints: Ensure that the number of visitors aligns with your park's maximum capacity of 25,000 at peak times.

Compare peak and annual demand: Validate that your calculated demand supports both your peak capacity needs and overall annual attendance goals.

Hope this helps! Alessa :)

Similar Questions
Consulting
How to do deeper research on consulting firms?
on Nov 23, 2024
Global
8
1.2k
Top answer by
Andrea
Coach
Senior Manager @ Bain & Company, with 100+ candidates interviewed
52
8 Answers
1.2k Views
+5
Consulting
How would you approach this market entry case
on Aug 27, 2024
Global
4
1.2k
Top answer by
66
4 Answers
1.2k Views
+1
Consulting
Could someone help me with a high level framework for this prompt?
on Jan 19, 2025
Global
5
900+
Top answer by
Evelina
Coach
EY-Parthenon (7 years) l BCG offer holder l 97% success rate l 30% off first session l free 15' intro call l LBS
26
5 Answers
900+ Views
+2