Hi,
For calculating Capex to roll out the fibre cost, why 250 HH were considered and not 125? The information mentioned that 50% of the HH subscribe for the broadband - in that case, shouldn't the Capex be - $1000 * (125 HH * 0.5 km per HH) = $ 62500??
Thanks in advance for clarifying this question. :)
Best regards,
Kirti